Hills were quantity surveyors for a new building to house a PET Scanner at the University Hospital of Wales. This was achieved over two phases.
Phase 1: Construction of a new eight-storey shell and core building including basement of concrete frame and cladding construction to provide future accommodation for hospital departments.
Phase 2: The fit-out of the shell and core building for the provision of a PET Scanner.
Phase 1: JCT Standard Form of Building Contract with Quantities; Phase 2: JCT Standard From of Building Contract without Quantities